Chimney Project

Public Power Factory
Chimney
in Atherinolakos, Crete

Public Power Factory <br> Chimney <br> in Atherinolakos, Crete 1
Public Power Factory <br> Chimney <br> in Atherinolakos, Crete 2
Public Power Factory <br> Chimney <br> in Atherinolakos, Crete 3

The height of the chimney is 80 metres.

TA 5-ton winch is mounted on the sliding type for lifting concrete and iron reinforcement.

As can be seen in the above photos, the sliding press has three levels of work:

  1. The main working floor where concrete is laid and the horizontal reinforcement is installed.
  2. The elevated working floor for the installation of vertical reinforcements
  3. The underlying working floor under the slipform shuttering, to form the surface of the concrete if required.

The outside surface is covered with a safety net.